    Govt defers ML-3 for third time

    Sajal Ali•November 15, 2026• 5 min read
    Text Size
    Govt defers ML-3 for third time
    National CoverageAman-e-Pakistan Digital Desk
    Key Story Executive Summary
    Quick Read

    “The government has deferred the approval of a $1 billion Mainline-3 rehabilitation project of Pakistan Railways, which has been conceived to transport minerals from Reko Diq mines, due to funding cons…”

    The Central Development Working Party (CDWP), for the third time in the past five months, deferred approval of the Rs278 billion, or $1 billion, up-gradation of ML-3 track from Nokhandi to Rohri this month, officials. The 996-kilometre-long track has outlived its life, and trains are crawling at an average speed of 30 km per hour.

    It requires a complete rehabilitation to make it viable for heavy cargo of minerals to be extracted from the Reko Diq mines. Government officials said that the project's approval had been postponed due to funding constraints and the possibility that the Reko Diq Mining Company, being run by Barrick Gold, could use Gwadar Port for the transportation of minerals.

    The project was deferred for more information and details about bridge financing with Barrick Gold, said Ahsan Iqbal, Federal Minister for Planning, while responding to a question. The government had already approved to take a $390 million loan from Reko Diq Mining Co at an estimated rate of 6% per annum as bridge financing to complete the ML-3 track.

    Key Story Takeaway

    "Stay connected with Aman-e-Pakistan for ongoing live reporting and verified investigative updates."

    The official said that in case of any change in the plan to use Gwadar Port instead of Karachi Port, fresh commitments were also needed from the mining company on whether it would extend the loan. The up-gradation of the track had been proposed to transport minerals through the Nokhandi-Quetta-Rohri and Karachi rail track.

    Sources said that there was a possibility that the minerals might now be transported through Gwadar Port, which would require making fully functional the Nokhandi-Panjgur and Gwadar road link.

    The development came in the middle of renewed focus on Pakistan's mineral potential, and this week the executives of three companies, Barrick Gold, Ivanhoe Atlantic and Minmetals, addressed the Pakistan Minerals Investment Forum. Also, a delegation of Barrick Gold Company met with Planning Minister Ahsan Iqbal this week and sought details of the road project that could be constructed, discussions.

    An official statement issued after the meeting read that Ahsan Iqbal "emphasised the need to fast-track the Nokhandi-Gwadar road corridor through close collaboration between the federal government, the government of Balochistan and mining companies to fast-track logistics connectivity. Earlier, the project was considered twice by the CDWP, first in June and then in August.

    In the second last meeting, the CDWP decided "the project is kept on hold until the Ministry of Railways provides a consolidated picture of its funding requirements for the next five years, indicating the funding to be arranged from its own resources, the requirement from PSDP, and any alternative financing arrangement without PSDP funding".

    While addressing the mineral forum, Prime Minister Shehbaz Sharif and Chief of Defence Forces Field Marshal Syed Asim Munir emphasised the need to export finished mineral products instead of just the raw material. The Quetta-Taftan rail section is also part of the transport corridor between Pakistan, Iran and Turkiye.

    All passenger and freight traffic of the Railways passes through this section to Iran and Turkiye. However, owing to the poor and dilapidated condition of the track, rail traffic has been drastically reduced. At present, one or two freight trains per month ply between Quetta and Taftan.

    The government hopes that after rehabilitation of the ML-3 track, freight traffic up to eight sets of freight trains and other freight trains towards Iran and other countries will give a boost to freight traffic manifold and resultantly revenue generation.

    However, the Planning Commission observed during project scrutiny meetings that project documents were silent about the consultation and coordination held with Reko Diq Mining Company., the company had promised funding through bridge financing, which the government was supposed to return by June 2028 through a bullet payment.

    For the current fiscal year, only Rs250 million has been allocated for the project. The Planning Commission was of the view that if the funding could not be arranged, then the project would be delayed and, as a result, the cost would increase tremendously based on experiences in the case of railway projects.

    At the agreed interest rate, the total repayment to the company will be nearly $450 million,. They said that during review meetings, Ahsan Iqbal also inquired from the Ministry of Railways about the source of funding, as it would not be possible to fund the project through the Public Sector Development Programme (PSDP).

    The minister had also directed the Ministry of Railways to provide a consolidated picture of its funding requirements for the next five years, including the proposed works on ML-3, ML-2 and ML-1. The minister stated that the Ministry of Railways should undertake projects, observing that its development portfolio was limited to around Rs40 billion.

    The government is already struggling to arrange funds for the ML-I (Karachi-Peshawar) project and is looking for multiple options, including a loan from the Asian Development Bank, a Frontier Works Organisation-led lease model and pledging the railways' land with the domestic commercial banks.

    S

    Written by Sajal Ali

    Aman-e-Pakistan Senior Journalist & Bureau Reporter

    Fact Checked & Verified

    Continue Reading: More in National

    Swipe or click arrows to explore National desk coverage

    CM Maryam approves Rs50m for each Punjab village upliftNational

    CM Maryam approves Rs50m for each Punjab village uplift

    Read Story
    Concern over KP healthcare system as 200 hospitals remain closed for yearsNational

    Concern over KP healthcare system as 200 hospitals remain closed for years

    Read Story
    PM resolves to continue operations against terrorists with full forceNational

    PM resolves to continue operations against terrorists with full force

    Read Story
    SC says time cannot erase inheritance rightsNational

    SC says time cannot erase inheritance rights

    Read Story
    Water minister inspects Tarbela intake structureNational

    Water minister inspects Tarbela intake structure

    Read Story
    Deputy collectors to lead anti-smuggling unitsNational

    Deputy collectors to lead anti-smuggling units

    Read Story